What is the critical path for the network below?
This project has three network paths
Path 1= Start -B-G-I-End = 4+8+ 6 = 18
Path 2= start-A-C-E-H-End = 6+4+6+5 = 21
Path 3 = Start-A-D-F-H-End = 6+5+6+5 = 22
The critical path in this network is start - A-D-F-H-End with the path value of 22.
The critical path of a network is the: Path with the fewest activities Shortest-time path through the network Longest-time path through the network Path with the most activities End run around the network
The critical path for the network activities shown below is __ with duration ___ Activity Duration Immediate Predecessors A 2 - B 4 - C 1 A,B D 6 A,B E 3 B,C,D
Calculate ES, EF. LS, LF and Float for the network shown below. Highlight the critical path. 5 6
NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...
(3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...
For the following, draw the node network, perform the CPM calculations, mark the critical Path, and complete the table. IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
Perform the CPM calculations for the following network diagram. Identify the critical path. PE
For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times a. Activity-on-arrow diagram 4 2 10 5 12 3 4 The critical path is (Click to select) The expected project duration is
W4A2: Tasks: See above to view the network diagram. Using the diagram, find: -The critical path. -How long it will take to complete the project? -How does simulation determine the probabilities of various project completion times? -What is "slack" and why is it important? -Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? -How is the uncertainty in project scheduling dealt with? -Should the critical path activities be managed differently from noncritical path activities? Explain....
Describe PERT network analysis and explainn the relationship between Slack Time and the Critical Path