Question

Computing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract in 202

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Part a $
1 Recognized Revenue    8,14,286
2 Gross Profit    2,44,286
3 Adjusted Contract Margin 30.00%
Part b $
1 Cumulative Recognized Revenue 15,33,333
2 Cumulative Gross Profit    3,83,333
3 Cumulative Adjusted Contract Margin 25.00%
Add a comment
Know the answer?
Add Answer to:
Computing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Computing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract...

    Computing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract in 2020 to provide computer equipment for $2 million. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $1.4 million. The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any costs incurred by Supplier Corp. plus a specified profit margin will be...

  • Print Question 6 Answer saved Marked out of 6.00 P Flag question Computing Revenue and Gross...

    Print Question 6 Answer saved Marked out of 6.00 P Flag question Computing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract in 2020 to provide computer equipment for $2 million. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $1.4 million. The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...

  • On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT