Question

14. A simple project listing of five actolt estimates are presented below: Immediate Predecessor Iime in Davs 3 None B and C 4 Using the Single Time Estimate CPM procedure, what is the finish time for the las project (i.e., the total time to complete the project)? A. 10 days B. 7 days C. 8 days 12 days 9 days
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

C . 8 days

the finish time for the last activity project is 8 days   

Add a comment
Know the answer?
Add Answer to:
14. A simple project listing of five actolt estimates are presented below: Immediate Predecessor Iime in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Save Ansv 1 A company must perform a maintenance project consisting of seven activities. The activities,...

    Save Ansv 1 A company must perform a maintenance project consisting of seven activities. The activities, their predecessors and their respective time estimates are presented below Immediate Activity Designation Predecessor Time in Days Break down both machines A None 3 Clean machine 1 B A 3 Clean machine 2 с A 3 Re-set machine 1 D B Re-set machine 2 E с 2. Re-calibrate both machines F D and E Final test F 2 Using CPM what is the Latest...

  • A simple CPM network has three activities, A, B, and C. A is an immediate predecessor...

    A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5. The network has no critical path. The critical path cannot be determined without knowing PERT expected activity times. The critical path is A-C, duration 10.5. The critical path is A-B-C, duration 9. The critical path is A-B-C, duration 12.

  • Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

    Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?

  • Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A      &n

    Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A          2 days              None B          5 days              A C          4 days              B D          9 days              A E          4 days              B & D F          12 days            E & C Draw a network diagram. Identify the critical path, earliest start and finish and slack for each task. Using MS Excel, produce a Gantt chart for this project. What would happen if a new estimate for task D increases...

  • The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...

    The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

  • Question 14 Not yet answered A simple CPM network has five activities, A, B, C, D,...

    Question 14 Not yet answered A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of Cand of D.B is also an immediate predecessor of Cand of D. C and D are both immediate predecessors of E. Which of the following statements is true? Points out of 1.00 P Flag question Select one: a. There are four paths in this network b. There are three paths in this network. c. There are...

  • From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2...

    From this schedule of activities: Activity Immediate Predecessor Activity Time A --- 4 B A 2 C B 3 D B 5 E A 1 F C, D 3 G E, F 2 a. Draw the PERT/CPM network b. Complete the forward and backward pass c. Determine the critical path d. Determine the total duration of the project.

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • A Question 11 The following table provides a list of activities in a project, along with...

    A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT