Question

1. Consider the simplified set of activities in Table 1 for the de velopment ofa consumer product from initiation through the market test phase. (a) Draw the AOA network for this project. (b) Calculate total slacks and free slacks, and interpret their meaning. (c) Determine the critical path and interpret its meaning. Table 1 Activity Symbol Preceding activities Time estimates Investigate demand Devel Design product Conduct promotional cost analvsis Manufacture Perform product cost analysis cing strate models Perform final pricing analysis Conduct market test B.D,F 2. For Question 1, consider the time estimates given in Table 2. Note that the time estimates in Question 1 are equivalent to most likely times in this exercise. (a) Assuming that the activity durations follow beta distributions, re-label your network in Question 1 to include d, (in place of d,) and s. Use equations: -b-, and 7-4 a 4m +b (b) Compare total slacks and free slacks to Question 1 if d, are used as the activity times. (c) Has the critical path changed? (d) Determine the probabilities that (1) The project is completed in 22 weeks or less. (2) The project is completed by its earliest expected completion date. (3) The project takes more than 30 weeks to complete. Table 2 Time Estimate (weeks) Most likel Activity timistic Pessimistic 12 10

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
1. Consider the simplified set of activities in Table 1 for the de velopment ofa consumer...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Consider the following table: Activity Initial Node Final Node Estimated Duration A 1 1 a. Draw...

    Consider the following table: Activity Initial Node Final Node Estimated Duration A 1 1 a. Draw an AOA network diagram for the above activity list for a project. b. What is the critical path for this project? c. What is the shortest possible time it will take to complete this project? d. What are the total slacks and free slacks for activity F and activity G?

  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • For the following project with times to complete activities in weeks: ActivityDepend on a m b...

    For the following project with times to complete activities in weeks: ActivityDepend on a m b 1 3 6 2 3 6 3 79 2 23 34 5 B,C (a) Calculate the expected time and variance for each activity. Draw the project network (AOA). Determine the critical path, expected completion time and variance. (b) Determine the probability of finishing the project in 14 weeks or less. (c) You want to tell the client you are 95% sure the project will...

  • The following table represents the set of activities required to complete a project, along with their...

    The following table represents the set of activities required to complete a project, along with their time estimates for PERT calculations. a. Using the data in the table, calculate the expected time (ET) and variance for each activity. Job Predecessor mi expected variance number Job(s) time (ET) --- 468 B A 3 4 5 CIA 234|| D C 34 11 E B, C 13 5 D, E 2 46 F b. [Sketch the network diagram for the project on a...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Given the following table, construct the network diagram, either AOA or AON. Times are in days a...

    Given the following table, construct the network diagram, either AOA or AON. Times are in days a. Determine the expected duration of the project. b.Compute the probability that the project will take at least 18 days. Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E

  • The table below defines the activities and the normal time duration for each activities within a...

    The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT