Question

10. You are a construction project manager and have identified that you project activities and resources are: Laborers Activi
0 0
Add a comment Improve this question Transcribed image text
Answer #1

given network Tolio 6,5 4 GB ole/ve] TISTS A, 20 C 6188 0,9 A, C slack is zero activities F are G cutical bez Total comp. timat yth & 8th days labour required increase by 2 labour (11-9) = 2. Since o is critical activity so cant be delayed. and henc] = o woo worron levelled resource allocation time I activity | resources I A 2 A. BICID B,C,D BICID B,C,D CD CD FID EFD E, F

Add a comment
Know the answer?
Add Answer to:
10. You are a construction project manager and have identified that you project activities and resources...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. For the following project draw a node network and a bar chart. Then perform resource...

    2. For the following project draw a node network and a bar chart. Then perform resource leveling trying to reduce the daily resources needed to no more than 8 laborers per day. If you cannot get it down to 8, manually shift resources so that the project starts low and gradually increases towards the middle and gradually decreases toward the end of the project Duration (days) laborers Activity IPA А 6 2 В 2 C 8 3 5 А, В...

  • o. 4 below are the resources and duration for a project Resources Activity Predecessor Duration Plumbers...

    o. 4 below are the resources and duration for a project Resources Activity Predecessor Duration Plumbers Laborers A,D 9 4 F,I Eleven plumbers and 9 laborers are available for this project. Both resources must work at the same time when assigned to the same activity. Prepare an activity schedule that satisfies the resource constraints. Part B Solve the problem using MS Project and show the total project duration. You should include Gantt and CPM Answer: Duration:

  • Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as...

    Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...

  • the project task: the new Project manager is appointed you for the construction of a new...

    the project task: the new Project manager is appointed you for the construction of a new warehouse on site. allocate resources to task(activity detail), present the cost estimates, with sub-totals at each level and overall estimated cost, discuss efforts to save costs, resources histogram.

  • A construction project is broken down into the following 10 activities:

    Problem 5-13 A construction project is broken down into the following 10 activities:b-1. What is the critical path? 1-4-7-9-10 1-3-6-9-10 1-2-5-8-10 1-3-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks _______ c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single-click the...

  • 2. In the following network, Draw the AON, calculate the early start and late start schedule,...

    2. In the following network, Draw the AON, calculate the early start and late start schedule, total and free floats, Allocate the resources, and level the resources for the following cases With a maximum of (8) laborer's per day. а. b. Level the resources to follow a normal distribution (start low, increase the resources gradually until it peaks in the middle, and then gradually decrease at the end of the project Duration Activity Predecessors laborers (days) A 2 В 2...

  • 3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

    3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time. Table 1: Activities, predecessors and duration time. Activity Predecessor Duration A - 2 B B 2 C A,B 1 D C,D 2 E D 3 Table 2: Activities and their required...

  • 3- Tables below show activities of a small project, predecessors, duration time, and resources that are...

    3- Tables below show activities of a small project, predecessors, duration time, and resources that are required (machines and workers). There are 3 machines and 4 workers available each day. Please use resource allocation algorithm to optimally allocate the recourses to the activities. Please specifies the project completion time. Table 1: Activities, predecessors and duration time. Predecessor Duration 2 Activity A B с D 2 1 B AB C.D D 2 E 3 Table 2: Activities and their required number...

  • Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR...

    Problem 5-13 A construction project is broken down into the following 10 activities: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) 1 — 5 2 1 3 3 1 4 4 1 2 5 2,3 6 6 3 4 7 4 2 8 5 4 9 6,7 7 10 8,9 5 b-1. What is the critical path? 1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 1-2-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks             c. If activities 1 and 10 cannot be shortened,...

  • Question #2. (20 marks) The following table shows activities related to a small project and their...

    Question #2. (20 marks) The following table shows activities related to a small project and their weekly usage of labors. Smooth (level) the resource usage so that a preferred resource usage is obtained. Activity IPA Duration week) Labor/week start start start Selo F G H Question #3. (15marks) For the project information of question2 above, and referring to the field report below, perform a revised schedule, then comment on it. At the end of week 5 the following field information...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT