Question

Question 2: (a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas...

Question 2:

(a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per daywithtasks, description of tasks, and time for each task shown in Table Q2a.

(i) Draw the precedence diagram anddetermine the cycle time,and number of workstations;

iii) Balance the line using the longest task time rule,and determine the line efficiency.

Table Q2(a)

Demand rate (units/day)

1225

Task

Time (sec)

Predecessors

Description

A

15

-

Open tool box and place on assembly line

B

9

A

Place spanner in tool box

C

7

A

Place spark plug spanner in tool box

D

7

A

Place screw driver in tool box

E

7

B, C, D

Close internal lid

F

18

E

Place jack in tool box

G

6

E

Place jack handle in tool box

H

7

Place polishing cloth in tool box

E

I

10

Close tool box

F, G, H

J

21

Shrink wrap tool box

I

(b) A company is unable to satisfy customer demand for one of their products. The ratios for mixing the outputs from processes C, D and E are 2, 1 and 1 respectively. The ratio for the departments F and G is 3 and 1, and the ratio for departments H and I is 4 and 1. Using Table Q2(b), Determine;

(i)The system capacityand bottleneck;

(ii) How much system capacity can be gained by adding capacity to the bottleneck

Table Q2(b)

Department

Capacity (liters/hour)

Predecessors

A

400

-

B

A

400

C

B

350

D

-

200

E

-

200

F

700

C, D and E

G

250

-

H

900

F, and G

I

300

-

J

1000

H and I

K

1300

J

0 0
Add a comment Improve this question Transcribed image text
Answer #1

2. a)

i) Given,

Total time = 8 hours = 8 x 60 x 60 seconds = 28800 seconds

Demand = 1225

=> Target cycle time = Total time available / Demand = 28800/1225 = 23.51 seconds \approx 24 seconds

Composite work content (Total time taken for tasks) = 15 + 9 + 7 + 7 + 7 + 18 + 6 + 7 + 10 + 21 = 107 seconds

=> Minimum number of workstations (Nmin) = Composite work content / cycle time = 107/23.51 = 4.55 \approx 5

The precedence diagram along with workstation distribution is shown below:

| Workstations 18 7 Workstation 1. A -- 6 e- - »I JA ro - workstation 5 7 Workstations workstation 4

ii) The Line is balanced and workstations are assigned using longest task time rule, i.e. the longest tasks available in precedence is added to a workstation. After the longest tasks are assigned, the shorter tasks are assigned to next workstation.

Hence, we have,

Workstation 1: Task A and Task B

Time = 15 + 9 = 24 seconds

Workstation 2: Tasks C,D and E

Time = 7 + 7 + 7 = 21 seconds

Workstation 3: Task F

Time = 18 seconds

Workstation 4: Tasks G,H and I

Time = 6 + 7 + 10 = 23 seconds

Workstation 5: Task J

Time = 21 seconds

Line balance efficiency = Sum of task times / Number of workstations x cycle time

= 107/ 24 x 5 = 107/120 = 0.891667 = 89.17%

2.b)

i) Bottleneck resource is the one that limits the overall process capacity or output.

We shall analyze how many liters of output from each resource is required for an input of 1 unit to the subsequent department.

Units of output per hour = Capacity/units required

For example,

For Department C,

Capacity = 350 liters/hour

units required = 2

Units of output per hour = 350/2 = 175 liters/hour of output

Department Capacity (liters/hour) Predecessors units required Units of output per hour A 400 1 400 B 400 A 1 400 350 B 2 175

Because the output per hour for department C is the least i.e. 175 liters, Department C is the bottleneck.

For process capacity:

We know C is the bottleneck and can contribute to making 175 liters of input for Department F.

Now, the 3 units of F are required to make 1 unit of H.

Hence, input for H = 175 / 3 = 58.33 Liters/hour

Now, the 4 units of H are required to make 1 unit of J.

Hence, input for J = 58.33 / 4 = 14.58 Liters/hour

Hence, process capacity = 14.58 Liters/Hour

ii) Now, we can add capacity to the existing bottleneck resource until the bottleneck gets shifted to the next limiting capacity of the resource.

Here, C is the existing bottleneck, and D and E are the next limiting resources.

So, we can add capacity to C till it matches the output from D and E.

C currently generates 175 liters of output per hour for which it requires a capacity of 350 liters.

We can increase C's output to 200 liters per hour, for which it will require 200 * 2 = 400 liters per hour of capacity.

Hence, additional capacity requirement = 400 - 350 = 50 liters/hour

Now,

the revised input to F will be 200 liters/hour

Now, the 3 units of F are required to make 1 unit of H.

Hence, input for H = 200 / 3 = 66.67 Liters/hour

Now, the 4 units of H are required to make 1 unit of J.

Hence, input for J = 66.67 / 4 = 16.67 Liters/hour

Hence, revised process capacity = 16.67 Liters/Hour

The gain in process capacity = 16.67 - 14.58

The gain in process capacity = 2.09 liters/hour

Note: Please like the answer, if it is helpful to you. Please mention the reason in the comment section, before disliking. Thank You.......!

Add a comment
Know the answer?
Add Answer to:
Question 2: (a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please answer step by step. Thank you. (b) A company is unable to satisfy customer demand...

    Please answer step by step. Thank you. (b) A company is unable to satisfy customer demand for one of their products. The ratios for mixing the outputs from processes C, D and E are 2, 1 and 1 respectively. The ratio for the departments F and G is 3 and 1, and the ratio for departments Hand I is 4 and 1. Using Table Q2(b), Determine; (i) The system capacity and bottleneck; (ii) How much system capacity can be gained...

  • Create a precedence diagram from the given table, then find a workstation assignment by taking cycle...

    Create a precedence diagram from the given table, then find a workstation assignment by taking cycle time=17 minutes and assigning in the order of the greatest task time. Task Label Time Predecessors A 2 ------ B 7 A C 5 ------ D 2 ------ E 15 C, D F 7 A, E G 6 ------ H 4 B, G I 9 A J 10 ------- K 4 ------- L 8 J, K M 6 A, L N 15 F, H,...

  • Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best...

    Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best line balance their production process. There are 12 steps to the production process, and they are presented below, along with their predecessors and how long it takes to complete each task. Assume all times are in minutes. This facility operates for 7 hours per day. Task C D E F G H I J K L A B Nil A B B B B...

  • For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A...

    For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.)    The minimum cycle...

  • Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach...

    Question d) The idle time for the assembly line per cycle = _____ minute(s) The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...

  • on Man HW Score: 2965 Score: 0 of 1 pt 3 of 3 (1 complete) Problem...

    on Man HW Score: 2965 Score: 0 of 1 pt 3 of 3 (1 complete) Problem 9.16 Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 10 minutes. Test Performance Predecessors Activity Activity Description Time (min) Predecessors A Attach wheels to tub B Attach motor to lid C Attach battery pack D Attach safety cutoff E Attach filters F Attach...

  • 2. Show all the steps for the question to be worth any marks. The following table...

    2. Show all the steps for the question to be worth any marks. The following table presentss the tasks, durations, and immediate predecessors necessary to produce a particular Rroduct The required daily output is 320 units, and the working day is 8.0 hours on an assembly line. Immediate Predecessor Duration (in minutes) Activity A 0.9 B 0.7 C 0.8 Г E 0.4 В, с А, D E 0.5 0.4 G E 0.6 Н F, G 0.5 T 1.1 a. Draw...

  • QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

    QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12

  • QUESTION 6 An industrial food processor needs to design a product layout for a new line...

    QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...

  • Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes:...

    Consider the following tasks, times, and predecessors for an assembly of set top cable converter boxes: TASK ELEMENT TIME (MINUTES) ELEMENT PREDECESSOR A 2 — B 1 A C 5 B D 4 B E 3 C, D F 3 A G 2 F H 1 G I 4 E, H Given a cycle time of seven minutes, what is the efficiency of your layout? Use the longest task time as primary criterion with largest number of following tasks as...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT