Question
Please help me answer all the questions. Please show work so I can understand the process. Thanks! (:
Problem #1 (8 points) 41 Given a table of activities associated with a project, their durations and preceding activities: act
0 0
Add a comment Improve this question Transcribed image text
Answer #1

PERT refers to Program evaluation and review technique where networks are used to plan and control the project and CPM refers to critical path method where shortest path is taken to plan the project. The objectives of PERT/ CPM are: -

  • Plan is made visually that help the project team to understand the progress and direction.
  • Project completion time can be determined.
  • Brainstorming what needs to be done.
  • To identify the task that require tight control.
  • To identify task that is critical for completion time.

s0l EF= ES+ duraton LE mininmers (iet | LS- LE-duration LF- EF LS -S2 8Date: S: 3 O A S 0 C1 ให้부 cve ˙ 부-3.weeb-+-E-by-4-weeks

Add a comment
Know the answer?
Add Answer to:
Please help me answer all the questions. Please show work so I can understand the process....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay​ Ishfaq's software firm in​ Chicago, their durations and what activities each must​ precede: Activity Duration​ (weeks) Precedes A​ (start) 2 ​B, C B 2 E C 6 F E 3 F F​ (end) 4 — This exercise contains only parts​ b, c, and d. ​b) Define the critical​ path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...

  • for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statisti...

    for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...

  • Please show me the answer and how to place it on a spreadsheet. Thanks. 13.7 Table...

    Please show me the answer and how to place it on a spreadsheet. Thanks. 13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration(Weeks) Activity Precedes 3 A(start) В.С В 2 5 C F E 2 F F(end) b- The activites on the critical path are: A C- F c- The total project completion time for Rafay Ishfaq's software firm is weeks. d- Determine the slack time for each of the activities. e- What is the total...

  • The following is a table of activities associated with a project at Rafay Ishfaq's software firm...

    The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • 6. A project has been defined to contain the following list of activities, along with their...

    6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...

  • und BOX your final answers to each part! part of the following questions. For full credit,...

    und BOX your final answers to each part! part of the following questions. For full credit, you MUST 1) The following activities are part of a project to be se project to be scheduled using the critical path method. Activity Duration (hours) Immediate Predecessors None A Mole А с B.D D E,F (a) Draw the network using the AON method. (3 points) (b) Identify the critical path. Box your answer. (3 points) (c) Calculate the slack available at any n...

  • 6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date:...

    6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date: Wednesday 6/11/2019 ( Total Raw Paints 20 Objective: This assignment is intended to provide you with an opportunity o e scheduling network analysis techniques using CPM and PERT.Ih sllaborations.of ans kindwill.nteeleatel dge and skils in id igmentand Examine the Sollewing table of activities, with stochastic (peobabilistic) dution estimates and predecessoe information (duration estimates are in eck) for a small peoject AtyOpin M yPi Predeo...

  • These can be computed exactly using the normal distribution. Please show all working 6. Consider the...

    These can be computed exactly using the normal distribution. Please show all working 6. Consider the following project network and activity times (in weeks): Start Finish Activity | A BC DEFG H Time 15 376 73 10 8 a. b. c. Identify the critical path. How much time will be needed to complete this project? Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT