Question

Page < Use the following to answer questions 11-13 B(4) 6 12 D(6 6 12 A(2) C(2) 11. Given the network shown above, what is the earliest start time for activity D a. 4 b. 6 c. 8 d. 10 e. 12 12. Given the network shown above, what is the latest finish time for activity A? a. 0 b. 2* c. 4 d. 6 c. 8 13. Given the network shown above, what is the slack time for activity B? MacBook Air FS F6 F7 F8
media%2F3c6%2F3c65a5d1-7987-4439-8fe0-3d
0 0
Add a comment Improve this question Transcribed image text
Answer #1

2. “BTケナー wka v/ Lat 12 凸

Add a comment
Know the answer?
Add Answer to:
Page < Use the following to answer questions 11-13 B(4) 6 12 D(6 6 12 A(2)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С...

    A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 C 3 2 5 2 5 0 D 7 3 10 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Refer to the figure above....

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • 11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...

    11 The following activity times are given: Determine the following a) Earliest start time b) Earliest finish time c) Latest Start Time d) Latest finish time e) Critical Path Activity Completion time( in months) 1-2 5 1-3 6 1-4 2 2-5 3 2-6 1 3-5 3 4-5 0 4-7 2 5-8 9 5-7 5 7-8 4 6-9 7 8-9 3

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 17-11) Use this network diagram for questions 11 through 17. 1. What is the expected duration...

    17-11) Use this network diagram for questions 11 through 17. 1. What is the expected duration of the project? (enter a whole number) 2. What is the critical path for this project? 3. What is the early finish time for activity E? 4. What is the early start time for activity D? 5. What is the late finish time for activity C? 6. What is the late start time for activity B? 7. What is the slack time for activity...

  • Given is a CPM project network diagram as shown below. Activity Start A B C D...

    Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing...

    please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 13-19. Do you understand PERT charts? Refer back to Figure 13-11 and answer the following questions: a. Which activity or activities must be completed before activity C can begin? b. Which activity or activities must be completed before activity G can begin? c. Which activity or activities must...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT