Answer: Option (A) - 7 days
Solution:
From the given information, the network diagram for the project can be drawn as below:
From the network diagram, the values of ES, EF, LS, LF can be computed as below:
In the above diagram, we can observe that the ES, EF, LS and LF values for Activity C are as:
Early Start (ES) = 0
Early Finish (EF) = 3
Latest Start (LS) = 7
Latest Finish (LF) = 10
The latest start for Activity C is Day-7, it means that even if the activity C starts on 7th day, it will still get completed on the 10th day without changing the whole project's earliest completion time of 25 days.
Allowable delay in Activity C = Latest Start - Early Start
Allowable delay in Activity C = 7 - 0
Allowable delay in Activity C = 7 days
Please show your work. Table 7.5 Activity PredecessorTime (da A,B 10 D,E Using Table 7.5, how...
Using Table 2.13 below, if the expected time for activity E is changed to nine weeks, by how many weeks will the project's expected completion time increase? Table 2.13 (All activity times for the project are in weeks.) Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessors(s) A 3 4 5 --- B 5 7 9 --- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 CD G 7...
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...
These can be computed exactly using the normal distribution. Please show all working 6. Consider the following project network and activity times (in weeks): Start Finish Activity | A BC DEFG H Time 15 376 73 10 8 a. b. c. Identify the critical path. How much time will be needed to complete this project? Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the...
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! PLEASE SHOW ALL WORK IN EXCEL!!!!!!! SHOW CALCULATIONS / FORMULAS IN EXCEL!!!!!!!! HW 4- All work must be completed in 1 excel file that, when necessary, includes cells that make calculations. 1) Information on a project's activities is shown in the following table ctivity Immediate Predecessor Activity Time (wks) Total Budgeted Cost 25,000 4 28,000 16,000 10 44,000 36,000 B, D, E 55,000 B, D, E 80,000 21,000...
Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g d 5 h f,g 8 Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points...
Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?