Question

Please show your work.

Table 7.5 Activity PredecessorTime (da A,B 10 D,E Using Table 7.5, how many days can activity C be delayed without changing the whole projects earliest completion time? O 7 days O 0 days 2 days O 5 days

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: Option (A) - 7 days

Solution:

From the given information, the network diagram for the project can be drawn as below:

5 A3 8 lo lo 0 tH 3 NETWORK DIAGRAM 31

From the network diagram, the values of ES, EF, LS, LF can be computed as below:

In the above diagram, we can observe that the ES, EF, LS and LF values for Activity C are as:

Early Start (ES) = 0

Early Finish (EF) = 3

Latest Start (LS) = 7

Latest Finish (LF) = 10

The latest start for Activity C is Day-7, it means that even if the activity C starts on 7th day, it will still get completed on the 10th day without changing the whole project's earliest completion time of 25 days.

Allowable delay in Activity C = Latest Start - Early Start

Allowable delay in Activity C = 7 - 0

Allowable delay in Activity C = 7 days

Add a comment
Know the answer?
Add Answer to:
Please show your work. Table 7.5 Activity PredecessorTime (da A,B 10 D,E Using Table 7.5, how...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT