Question
Please answe all parts
4. The project below has been defined. Draw a network diagram for the project and assume that the project must be completed b
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) The shortest project duration is 27 Days

b) Seven tasks have slack greater than 0. They are Activities B,C,D,F,H,I and K.

c) The slack of task I is 1.

d) The slack of task K is 4.

Add a comment
Know the answer?
Add Answer to:
Please answe all parts 4. The project below has been defined. Draw a network diagram for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • DSIM 350: Managing Product and Service Operations Final Exam - Total Points (100) Problem 2: Ch...

    DSIM 350: Managing Product and Service Operations Final Exam - Total Points (100) Problem 2: Ch 9 Project Management (50 Points) Following table gives the details about all tasks needed to be completed for a pro their respective predecessors and task times (weeks). ject along with 1. Activity Activity predecessor Time (Weeks) b, c 7 6 4 a. Draw the network diagram b. Calculate ES-EF-LF-LS times and determine the slack for each activity. Show all calculations on the diagram. Establish...

  • B. Resource Loading (33 pts). The network diagram below represents a project plan. a. b. C....

    B. Resource Loading (33 pts). The network diagram below represents a project plan. a. b. C. Compute the early, late, and slack times. Include your diagram in your paper What is the project duration? What is the critical path -illustrate it on your diagram (such as a dotted line). Ch 8 Assignment Resources: P(ainter); T(rimmer) 0 A START P & T ES ID EF SL Resour LS Dur LF 2 As your text stated, a plan isn't a schedule until...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • 2) The following tasks been assigned for a project following the steps needed to develop a...

    2) The following tasks been assigned for a project following the steps needed to develop a project network. Show al necessary steps and graphical representations. Find: 1 Critical Path for this project 2) Total free slack times for each activity 3) Total completion Time 4) The latest time that the activity D must be started to complete the project by day 54 Activity Predecessor Activity Time A |None None M,L.K 3) How would you calculate the duration of an activity...

  • Please help me with this question (( clear draw Please)) Draw the network diagram, including all...

    Please help me with this question (( clear draw Please)) Draw the network diagram, including all calculations of nodes using the following format: Early Start Duration Early Finish Task Name Late Sta rt Slack Late Finish List the networkpaths below: Determine the criticalpath(s). What is it and what is its duration? Activity Duration Dependency Start 0 A 6 Start B 1 A C 3 A,B D 5 A, B E 12 Start F 4 D, E G 2 C, F...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...

    PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget      ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...

  • 2. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M...

    2. Consider the network described in the table below. Immediate Predecessor(s) Activity J K L M N O Р Pessimistic 15 9 10 3 9 10 10 J J KM KM LN Probable 10 8 6 3 5 7 8 Optimistic 8 7 5 3 1 4 3 Draw the network diagram and answer the following questions, DuC duUCULUU AabbLCU AOBOLcud Red E 1 Normal 1 No Spac... Heading 1 Heading 2 Title Subtitle Subtle Em... Sel Styles Edit Paragraph...

  • Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the...

    Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points) Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT