There are 6 activities in a company called A, B, C, D, E, and F. Activity A starts first, followed by other activities, but it must end with activity F. Draw the precedence diagram! If the company has 3 work stations, show at least five possible activity in work station 1, workstation 2 and work station 3! If the company has 4 work stations (WS), is it okay if in WS 1 is activity A, WS 2 is activity D, WS 3 is activity B and F, WS 4 is activity C and E? Explain why!
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Exercise (collect in room 1117) 1. We want to buy a machine.There are 3 options a. Manual machine, b. Semiautomatic machine, c. Automatic machine. Show these 3 machines on Cost versus Quantity graph (show 3 curves in 1 graph). Then, how to choose the machine based on the curve in the graph 2. Precedence diagram: First we have to do activity A, then we can do activiy B or C, AdtivityD can be done after B and C are finished,fialywe...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
Assignment #2 is to provide a problem statement, WBS diagram, activity listing, and precedence diagram. Deliverables for HW2 shall include: · A Project Statement For the attached example (see item 3 below), the Project Statement is: “Owner to design and build a new residence. Hiring and oversight of architectural, design, and construction professionals will be managed by the Owner. All materials and permits will be provided by the Owner.” · An Activity Listing The activity listing should be prepared and...
The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: А 3 B 2 A C 2 1 D E 1 B F 2 1 D D G H 4 2 BD E J 1 E F 4 K L 3 G M N 3 3 H 0 4 HKL P MNO...
Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...
Case-2 Consider that you have an interview in a construction firm and they asked you to develop an (AOA) network for a construction project has the following activities along with their relationships. Draw your suggested network. (15 Marks) (The project was started in activity A and it is the precedence of activities B,C,D &E, the activity B is followed by activity F, while the activity C was followed by activity G, the activity K was not start until the activities...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 5 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7 Carl's team should be able to complete the project in nothing days. Critical path activities for Carl's project are .
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 B 2 A C 2 D 1 E 1 B F G 2 1 D D H 4 BD 2 J J 1 4 K F L 3 G M N 3 3 IJ H 0 4 HKL MNO Р...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3 In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence...