Situation 4 Using relevant information on the table of Situation 3 and the probabilistic nature of...
Slattkey Sweets proposes to re-launch one of its mature brands, the Zubirot Bar. The brand man- ager has identified the tasks involved and produced the following information about them Activity Description Precedence Duration (weeks Redesign the bar Redesign the packaging Build pilot production line Trial production run Consumer panel tests Main pilot production Design promotional material Test market redesigned product Produce report for the Board 13 F, G 10 al Draw a network to portray this enterprise and use it...
Using the information provided in the table below, find the probability of completing the project in 44 weeks? Pessimistic Time Estimates Time Estimates (weoks) Optimistic Time Most Likely Immediate PredecessorisEstimate (wooks) Activity ) (weeks) A none A B 12 A C 10 B 12 18 F F D, E 6 D, E G 6 10 H 8 11 G 3 3 H I J
301247/mod_resource/content/B/Exam%202%20March%202020.pdf - + Fit to page Question 2) Use the table diagram below to answer the following questions? (20 Points) Time Estimates (days) Optimistic Most Likely Pessimistic Activity Start Precedes AB CD 56 D F F End a) Draw the project network? (5 Points) b) What is the expected duration and standard deviation for each activity? (5 Points) c) What is (are) the project critical path(s); duration(s); and standard deviation (s)? (5 Points) d) What's the probability that the critical...
The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...
Question 2 (50%): The project information is presented in Table 1. It is known that the critical path of the given project is A - D + G - J. 1) Please fill out the Table 2. (1% * 10-10%) 2) The duration of the project is days (10%) Note: Calculation processes for 1) and 2) are not required. 3) What is the probability of finishing the project in 18 days? (15%) 4) What is the probability of finishing the...
The project manager of Good Public Relations gathered the data shown in the following table for a new advertising campaign. Click the icon to view the table. a. How long is the project likely to take? (Make sure to round all intermediate calculations fort, to two decimal places.) The project is expected to take 36.01 weeks. (Enter your response rounded to two decimal places.) b. What is the probability that the project will take more than 36 weeks? Refer to...
(50 points) Data regarding the activities for a project are presented below. The times are in weeks The critical path for this project is A-D-H-I-J-K 2. Pessimistic Time Most Likely Time y Optimistic Time 8 16 10 8 10 12 8 14 5 6 2 a. Determine the standard deviation of the critical path. b. Determine the probability of completing the project in 38 weeks or less c What is the probability of completing the project in 32 weeks or...
Please use the table to answer questions, SHOW WORK Consider the following work breakdown structure for questions 46-50: Duration (Days) Most Start Finish Activity Node Node Optimistic Likely Pessimistic 50 31 70 41 35 59 34 82 41 58 32 30 5 46 What is the estimated expected (mean) time tor activity D? A 32 days B. 41 days C 44 days D. 42 days E 40 dayts 46 What is the estimated standard deviation for the critical path? A...
Predecessors below Worst Duration 10 Index Tasks Best Duration Most Likely Duration Market Research Cost Analysis Product Design Development Analysis Developing Product Model Filing Contracts Product Testing Pricing Sales/Marketing Planning Sales Force Training 12 10 13 16 18 15 10 12 12 10 a. Average duration and variance of each activity? The critical path on average is? b. c. d. e. f. The average duration of the critical path found in (b)? Variance of the duration of the critical path...
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.