Question

The following information pertains to a project that is about to commence. Determine the duration of...

The following information pertains to a project that is about to commence. Determine the duration of the Project, slacks, ES,EF,LS,LF & Critical path. Activity Precedes Estimated Duration (days) A B 15 B C, D 12 C E 6 D End 5 E End 3 F G, H 8 G I 8 H J 9 I End 7 J K 14 K End 6 ________________________________________

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Note the following rules to find Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack.

Forward pass

ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate predecessors)
EF of an activity = Its ES + Its duration

Backward pass

LF of ending activities = Max. (All EF's)
LF of all other activities = Min. (LS of their immediate successors)
LS of an activity = Its LF - Its duration

Slack = LF - EF

Activity Precedes Estimated Duration (days) ES EF LS LF Slack
A B 15 0 15 1 16 1
B C, D 12 15 27 16 28 1
C E 6 27 33 28 34 1
D End 5 27 32 32 37 5
E End 3 33 36 34 37 1
F G, H 8 0 8 0 8 0
G I 8 8 16 22 30 14
H J 9 8 17 8 17 0
I End 7 16 23 30 37 14
J K 14 17 31 17 31 0
K End 6 31 37 31 37 0

The critical path is constituted of activities with Slack = 0.

So, the critical path is F-H-J-K and the estimated duration of the project is 37 days.

Add a comment
Know the answer?
Add Answer to:
The following information pertains to a project that is about to commence. Determine the duration of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • : A network consists of the following list. Times are given in weeks. Activity Preceding Duration...

    : A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...

  • Problem #2 (25 points) For the project below, choose a random duration for each activity (Activity...

    Problem #2 (25 points) For the project below, choose a random duration for each activity (Activity A already has a duration of 3). Calculate the ES, EF, LS, LF, TF and FF for all activities. Use the legend shown below for each activity and highlight the critical path. Fill the answers in the activity's boxes shown below. F с E H A 3 D G Legend: ES TF EF FF Activity LS Duration LF

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A...

    Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project?

  • 5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark...

    5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...

  • Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for eac...

    Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the questions (a) Draw both the activity-on-arrow (AOA) network and the activity-on-node (AON) network. (b) Calculate the early start time (ES), early finish time (EF), late start time (LS), and late finish time (LF) of each activity, and identify the critical path. (c) Compute the total float (TF), free float (FF), interfering float (IF), and independent float (IDF) for each activity (Note: The duration of...

  • Question 5 For the project depicted below, a) Compute the ES, EF, LS, and LF times...

    Question 5 For the project depicted below, a) Compute the ES, EF, LS, and LF times for the network. b) Explain how the ES for Activity 3 is obtained. c) Explain how the LF time for Activity 1 is obtained. d) What is the critical path for the project? e) How long do you expect the project to take to complete? Activity 4 Activity 2 ES= EF= wks LSELF ES= EF T=5 wks LSELF= Activity 1 ES= EF= T=6 wks...

  • Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the...

    Construction Management Assignment on "Critical Path Method (CPM)" Do the following tasks for each of the questions (a) Draw both the activity-on-arrow (AOA) network and the activity-on-node (AON) network. (b) Calculate the early start time (ES), early finish time (EF), late start time (LS), and late finish time (LF) of each activity, and identify the critical path. (c) Compute the total float (TF), free float (FF), interfering float (IF), and independent float (IDF) for each activity (Note: The duration of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT