Question

Please provide detailed solutions to the following problem. The estimated times and immediate predecessors for the...

Please provide detailed solutions to the following problem.

The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent.

Activity

Immediate Predecessor

Time (Weeks)

a

m

b

A

-

9

10

11

B

-

4

10

16

C

A

9

10

11

D

B

5

8

11

a) Calculate the expected time and variance for each activity.

b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?

c) What is the variance of the critical path? What is the variance of the other path in the network?

d) If the time to complete path A–C is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

e) If the time to complete path B–D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?

f) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a) We find expected time and variance for each activity as shown below:

Based on above table, we prepare project network diagram as shown below;

b) Hence, as seen from above, A-C is the critical path. The expected completion of critical path A-C is 20 weeks The expected completion time of other path B-D is 18 weeks

c) Variance of critical path = variance for A + Variance for C = 0.11 + 0.11 = 0.22.

Variance for path B-D = variance for B + Variance for D = 4+1 = 5

d) Probability for completion within 22 weeks

Probability is found out by finding z value as follows:

z = = = 4.26

From normal distribution table, we get the probability for value of z = 4.26 as 100%

________________________________________________________________________________________________

Other questions have to be posted separately

Add a comment
Know the answer?
Add Answer to:
Please provide detailed solutions to the following problem. The estimated times and immediate predecessors for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT