Question

Dr. Thomas has been given a budget of $10,000 to organize a conference at her university...

Dr. Thomas has been given a budget of $10,000 to organize a conference at her university in 3 months’ time (12 weeks) via an educational grant. She has a team of 2 research assistants and after some deliberation, they identified the following activities that are required to be completed for hosting a successful conference.

Activity Description    Immediate Predecessor

A Planning Topics and Sessions    . .

B    Inviting presenters from various universities    A

C identifying potential venues in the city    . .   

D Selecting a venue for the conference C

E Finalizing presenters for each session B

F Completing registration for all presenters E

G Preparing agendas and inviting participants    D, E

H Last minute edits, replacements, and lists F, G

Thomas has approached you, her student, to help her figure this out, as a part of her Management Science class assignment. Please give your responses, with appropriate explanations, tables, and formulas, where relevant, to the following questions:Follow a PERT/CPM model to identify the project network, activity schedule, critical activities, and the expected time for completing the project successfully. The expected completion times for each of the listed activities is based on the experiences of all the people on the team and is as follows:

Activity    Optimistic    Most Probable Pessimistic

A    1.5 2    2.5

B    2 2.5 6

C    1 2 3

D 1.5 2 2.5

E 1.5 3    4.5

F 0.5    1 1.5

G 1    2    3

H    1 2 3

Dr.Thomas is worried about completing all the required activities before the 12-week deadline is up, because she has never hosted a conference before. She wants to know, based on her team’s estimates what is the probability of NOT completing the activities by the end of 12 weeks.In order to have some peace of mind, Dr. Ell decides that she is willing to pay her Research Assistants extra money, out of her own pocket, in order to complete the project within 10 weeks. She has identified the following crashing options for each activity.

Crashed Activity (cost ($)

Activity    Time Normal    Crashing

A    1 1,000    2,000

B 2 2,000 3,000

C 1.5    500 1,000

D    1.5 500 600

E 2    5,000 6,000

F 0.5 100    500

G    1    500 1,000

H 1    400 900

a. Write a Linear Program to help Dr. Thomas identify which, if any, activities should be crashed and how much that would cost her. Remember, since she is paying personally for the extra crashing time, she wants to minimize costs.

b. Provide a clear solution and present your case for her consideration by showing an updated activity schedule, and presenting the probability of getting the whole project completed within 12 weeks, if she decides to implement the crashing of activities. What is the probability of getting the whole project completed within 11 weeks? For the sake of simplicity, you can assume that the variances will not change for the crashed activities.

c. Perform a sensitivity analysis to identify if she can reduce her costs further by allowing an 11-week deadline instead of a 10-week deadline and explain if she should aim for 11-weeks instead of 10 weeks and why (or why not).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Using PERT, the expected project duration comes out to be 12 weeks. However, the standard variation for the same is 0.972 making the probability of completion within 12 weeks to be 0.5

Kindly refer the solution below for details. The activities are crashed and the new probabilities of project completion within 10 and 11 weeks are determined.

Add a comment
Know the answer?
Add Answer to:
Dr. Thomas has been given a budget of $10,000 to organize a conference at her university...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project ....

    Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...

  • oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered...

    oblem S.ST evelopmient of Version 2 0 of a particular accounting software product is being considered by Jose Noguera's ompletion of this projedt are listed in the following table: technology firm in Baton Rouge. The activities necessary to Total Cost Normal Time Crash Time Normal with (weeks) Cost Crashing Immediate Predecessors) S2,000 $2.600 S2,300 $3,100 S750 $750 S2,500 $2.780 $1,000 $1,375 $3.000 S4,200 $1400 $2.000 D E a) Based on the given information regarding the activities for the project,the project...

  • 1) Based on the given information regarding the activities for the project, the project length= ___...

    1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...

  • I ONLY need help on letters G and I. According to the answers I've tried for...

    I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...

  • 6. A project has been defined to contain the following list of activities, along with their...

    6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc....

    Development of a new deluxe version of a particular toy is being considered by T-O-Y Inc. The activities necessary for the completion of this project along with the relevant information for each activity are listed in the following table. The Total Crash Time represents the time for that activity after it has been crashed the maximum crash time allowed for that activity. For example, we can reduce the time for Activity A by one week to 3 weeks after crashing...

  • Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,000...

    Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000      DA543,5004,000EB434,7505,500FC222,0002,000      GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT