Question

The Hindenburg Corporation (SC) signed a $6 million contract in 20x1 to build an office tower. Data on the contract is as fol
0 0
Add a comment Improve this question Transcribed image text
Answer #1

aSnput mepaod 2011 1 couplepion 1600D00 16000003400000 = 31 Revenue Cost 1.920000 4 (1.6oס oco s +ag Ned Snweltuend in the faNer nenet inte 2 Cuss! tel dlat 3 100 D00 74,800 - (2500 000) C- ovne Receved Custouel Znwnt clue ou cutome 1,3+C 80 2013 1.>De Snuestmens 3 date 5,300000 C+) Pfit C-Amane Receved ou Cuttouel C6000000) NO tofrou Cuttones b Ouppus mmereop ParPrcularsJnvertmens in RIS 4 201e Partculas 2011 2013 2012 Lust e ate 1,600DO0 3100 0o04(O0 000C300 000 (00000 C) Protit 400000 00 0OU

Add a comment
Know the answer?
Add Answer to:
The Hindenburg Corporation (SC) signed a $6 million contract in 20x1 to build an office tower. Data on the contract...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....

    Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? 18. Tullis Construction enters into...

  • At the beginning of 2013, the Harding Construction Company received a contract to build an office...

    At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $2,300,000...

  • Tullis Construction enters into a long-term fixed price contract to build an office tower for $10.400.000....

    Tullis Construction enters into a long-term fixed price contract to build an office tower for $10.400.000. In the first year of the contract Tullis incurs $2,250,000 of cost and the engineers determined that the remaining costs to complete the project are $4,000,000. Tullis billed $3,700,000 in year 1 and collected $3,500,000 by the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? (Round any intermediary percentages to the...

  • During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The...

    During 20x5, the Ibti Construction Company obtained a $15 million contract to build a bridge. The costs incurred, estimated costs to complete and the billings made on the contract for the period 20x5 – 20x6 are as follows: 20x5 20x6 Costs incurred during the year $3,000,000 $5,000,000 Expected costs to complete 9,000,000 6,000,000 Billings 7,500,000 - Ibti uses the percentage of completion method. Costs incurred relative to total project costs are used to measure the percentage of completion at the...

  • Bright Future signed a $700,000 contract to an d the project required three years to complete....

    Bright Future signed a $700,000 contract to an d the project required three years to complete. Bright Future estimated that total contract coswabe SGD 000 The financial information during 2031 203 related to the construction contracts as the following 2002 2003 Costs incurred to date $200.000 $370,000 $610,000 Estimated costs to complete 400 000 250.000 Progress bilings made during the year 210,000 315.000 175.000 Collections of billings during the year 200,000 320,000 180,000 Additional information: 1) The customer does not...

  • Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee...

    Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee contract specifies that the facility is to be completed in three years. Bigelow uses the percentage-of-completion method (cost-to-cost approach) to account for its construction transactions. Information related to this contract is summarized in the following table. Contract price $ 2,000,000 2018 2019 2020 Actual construction costs incurred during the year $ 900,000 $ 300,000 $ 600,000 Construction costs incurred in prior years 0 900,000...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Cons...

    Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT