Question

ou are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given...

ou are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path.


ID Description Predecessor Time
(days)
A Systems None 2
B Subsystem A design A 1
C Subsystem B design A 2
D Subsystem C design A 1
E Program A B 2
F Program B C 10
G Program C D 3
H Subsystem A test E 1
I Subsystem B test F 1
J Subsystem C test G 1
K Integration H, I, J 3
L Integration test K 1

How Long will this project take?(answer in days)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Nelwork dingraus H ES: ely Ef: ear fini ES pciuEF fer forwand LS: lati starp durloLf LS Lf: Jata for back wsand pass (-

This is the network diagram showing all the activities with their predecessors. A matrix is shown which is used further to solve the problem. Here :

ES stands for early start, and it means earliest an activity can start given its predecessor finishes early.

EF stands for early finish.

LS stands for late start. This happens when predecessor activity finishes late.

LF is late finish.

Using the matrix defined in above sheet ES,EF,LS,LF timings are obtained using forward pass and backward pass method.

Forward pass gives us ES and EF timings and backward gives us LS and LF timings.

Slack as defined in image is EF-ES or LF-LS. Value of each activity slack is calculated and shown above each matrix.

Critical path is the one in which all the activities have zero slack. Hence here critical path is A<C<F<I<K<L.

As activity L is the last activity of critical path it's finish time is the duration of project. Hence project duration is 19 days

P.S. : kindly give feedback

Add a comment
Know the answer?
Add Answer to:
ou are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

    QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12

  • Management Information Systems Assume you have a project with 11 activities labeled A - K (below)....

    Management Information Systems Assume you have a project with 11 activities labeled A - K (below). (5 points) Activity Preceding Activities Duration (Days) Early Finish (Days) Late Finish (Days) Free Slack (Days) A -- 4                   B A 2                   C B 6                   D B 21                   E B 12                   F C, D 2                   G D, E 15                   H F, G 8...

  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • The total future years of productivity, X, of a draft round 1, of a major league...

    The total future years of productivity, X, of a draft round 1, of a major league baseball player has the density function: f(x)= x'e-* for OSXS and 0 otherwise. a)What is the probability that the player lasts no more than 5 years? b) What is the probability that X > 5? c) What is the probability that 3< x < 9? d) What is the expected future years of productivity, X, of a round 1 draft pick, of a major...

  • I need help Software Project Management question Q1. For the following table of information:        a)...

    I need help Software Project Management question Q1. For the following table of information:        a) Draw a network diagram (Activity on Arrow)        b) List down all the network paths        c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Florida Power & Light is attempting to modernize the meters placed at people houses. The company...

    Florida Power & Light is attempting to modernize the meters placed at people houses. The company Operations Manager, Mr. Jacob Marina, has asked for your assistance in preparing part of the project plan. Mr. Marina has identified the tasks, durations (in days), and predecessor relationships, and provides them in the following table: Immediate Most Activity Predecessor(s) Optimistic Likely Pessimistic A -- 1 2    4 B A 2 4    8 C B 3 5 15 D C 3 5 12 E...

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT