Question

Activity U cannot begin until both activities S and T have been completed. Activity V cannot...

Activity U cannot begin until both activities S and T have been completed. Activity V cannot begin until both activities S ad T have been completed. The duration for U,V, and T are 23,11,70, and 41 days, Respectively. if the earliest start time for S is at the end of day 53 and the earliest start for T is at the end of day 51, the earliest finish time for V is at the end of day______?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Since we have to know earliest finish of V, we will analyse network path for V only. V cannot start till S and T are completed

Early start for S = End of day 53, duration = 70 (Assumed 70 since not clearly mentioned in question)

Early finish of S = 53+70=End of day 123

Early start for T = End of day 51, duration = 41 (Assumed)

Early finish for T = 51+41=End of day 92

Since early finish of S > early finish of T, S governs.

Hence, early finish of V = Early finish of S + Duration of V = 123 + 11 = End of day 134

Answer:134

Add a comment
Know the answer?
Add Answer to:
Activity U cannot begin until both activities S and T have been completed. Activity V cannot...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT