Activity U cannot begin until both activities S and T have been completed. Activity V cannot begin until both activities S ad T have been completed. The duration for U,V, and T are 23,11,70, and 41 days, Respectively. if the earliest start time for S is at the end of day 53 and the earliest start for T is at the end of day 51, the earliest finish time for V is at the end of day______?
Since we have to know earliest finish of V, we will analyse network path for V only. V cannot start till S and T are completed
Early start for S = End of day 53, duration = 70 (Assumed 70 since not clearly mentioned in question)
Early finish of S = 53+70=End of day 123
Early start for T = End of day 51, duration = 41 (Assumed)
Early finish for T = 51+41=End of day 92
Since early finish of S > early finish of T, S governs.
Hence, early finish of V = Early finish of S + Duration of V = 123 + 11 = End of day 134
Answer:134
Activity U cannot begin until both activities S and T have been completed. Activity V cannot...
Activity U cannot begin until both activities S and T have been completed. Activity V cannot begin until both activities S and T have been completed. The duration for U, V, and T are 53,50,37, and 31 days, Respectively. if the earliest finish time for S is at the end of day 108 and the earliest start time for T is at the end of day 77, the earliest finish time for V is at the end of day______?
Using precedence diagramming method, activity B must not start until activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. What is the correct description of the type of the relationship that exists between activites A and B This relationship is an example of the rare but occasionally necessary Start-Finish relationship, SF-3d. This relationship is a standard Finish-Start relationship, FS, but the successor of B will have a 3 day...
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
Consider the following variation on the Activity Selection Problem.You have a resource that may be used for activities 24 hours a day,ever day.Activities repeat that may be used for activities repeat on a daily basis. As in the original problem, each activity has a start time and as end time.If an activity is selected, it will exclusively use the resource during the duration between the start and end time(i.e., no other activity may be scheduled during this time). Note that...
Please the question consists of (a) , (b) and (c). I need the crashing part which is the (c) than everything. Is very urgent Question 7 The Family Entertainment Group is about to begin the production of its most Ebo Whyte, ensive) movie of the year. The movie's producer, Mr. project. He has identified the eight major activities (labe and H) rcquired to produce the movie. Activities weeks respectively, cannot start until activity A completed. Activities E and F tak...
Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 5.13. It...
Question 1 10 points Save Answer A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run 1 A Duration B Duration C Duration 51 48 17 60 48 19 2 3 30 39...
Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...
F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...