Activity U cannot begin until both activities S and T have been completed. Activity V cannot begin until both activities S and T have been completed. The duration for U, V, and T are 53,50,37, and 31 days, Respectively. if the earliest finish time for S is at the end of day 108 and the earliest start time for T is at the end of day 77, the earliest finish time for V is at the end of day______?
The given information along with the dependency is captured in the network diagram below
We know that earliest finish time of the activity is given by adding the duration of the activity to its earliest start time. Also, the earliest start time of any successor activities is the higher of the earliest finish time of all the predecessor activities.
As we need to find earliest finish time of activity V, we need to find the earliest finish time of its predecessor activities S and T. The earliest finish time of activity S is given as 108. The earliest finish time of activity T is the sum of earliest start time of T which is 77 and duration of T which is 31. Hence earliest finish time of T is 77+31 = 108.
The earliest start time of activity V is than higher of earliest finish time of activity S and T. In this case both these activities have the same earliest finish time which 108. Hence the earliest start time of activity V is 108. Hence earliest finish time of activity V is the addition of 108 and it duration. Hence earliest finish time of activity V is 108+50 = 158 days.
Hence the earliest finish time of activity V is 158 days.
Activity U cannot begin until both activities S and T have been completed. Activity V cannot...
Activity U cannot begin until both activities S and T have been completed. Activity V cannot begin until both activities S ad T have been completed. The duration for U,V, and T are 23,11,70, and 41 days, Respectively. if the earliest start time for S is at the end of day 53 and the earliest start for T is at the end of day 51, the earliest finish time for V is at the end of day______?
Using precedence diagramming method, activity B must not start until activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. What is the correct description of the type of the relationship that exists between activites A and B This relationship is an example of the rare but occasionally necessary Start-Finish relationship, SF-3d. This relationship is a standard Finish-Start relationship, FS, but the successor of B will have a 3 day...
You are STA FIN The duration of activity K, M, N, and P are 36, 39, 26, and 35 days, respectively. The duration of activity E, F,G, and H are 24, 27, 32, and 37 days, respectively The latest start times of activity Q, R, and S at the end of day of 95, 99, and 85, respectively. Perform the backward pass of CPM The latest finish time of activity E is at the end of day The latest finish...
1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...
.8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...
Consider the following variation on the Activity Selection Problem.You have a resource that may be used for activities 24 hours a day,ever day.Activities repeat that may be used for activities repeat on a daily basis. As in the original problem, each activity has a start time and as end time.If an activity is selected, it will exclusively use the resource during the duration between the start and end time(i.e., no other activity may be scheduled during this time). Note that...
Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 5.13. It...
F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...
Given the following information, Construct the PDM network and use the information given in the following table, calculate ES, EF, LS, LF and the critical activities. Project Data: 1-U and R can be performed concurrently and both begin on the start of the project. 2-Activity X is independent of both activities Q and K 3-E must start before work on activity K can begin. 4-Neither activity F nor activity G can start before activity R start. However, activities F and...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...