Question

5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a contract price of P8,400,000 payable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct answer is option D P 1,100,000

Working

By December 29, 2016 3/4 of the building had been completed.

Percentage of completion on an output basis proportional method = 75% (3/4 of the project)

Revenue to be recognised = 8400000*75% = P 6,300,000

Cost incurred till date = 4200000+1000000 = P 5,200,000

Gross Profit = 6300000-5200000 = P 1,100,000

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Correct answer in option B P 1,040,000

Working

By December 29, 2016 3/4 of the building had been completed.

Percentage of completion on an actual cost approach = cost incurred till date/Estimated cost of completion

Cost incurred till date = P 5,200,000

Estimated cost of completion = P 7,000,000

Percentage of completion on an actual cost approach = 5200000/7000000

Revenue to be recognised = 8400000*(5200000/7000000) = P 6,240,000

Cost incurred till date = 4200000+1000000 = P 5,200,000

Gross Profit = 6240000-5200000 = P1,040,000

Add a comment
Know the answer?
Add Answer to:
5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a...

    5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a contract price of P8,400,000 payable in 5 installments. One-fifth of the contract price was to be paid upon completion of each quarter of the work (as defined in detail by thr terms of the contract), the final payment being due within 10 days after acceptance of the completed project. By December 29, 2016, 3/4 of the building had been completed whereupon the third billing...

  • 5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a...

    5) Lovely Construction Co. was engaged on October 1, 2016 to construct a building for a contract price of P8,400,000 payable in 5 installments. One-fifth of the contract price was to be paid upon completion of each quarter of the work (as defined in detail by thr terms of the contract), the final payment being due within 10 days after acceptance of the completed project. By December 29, 2016, 3/4 of the building had been completed whereupon the third billing...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M....

    Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M. cost information over life of the contract is as follows 5.16 Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1,100,000 Estimated Cost to Complete $5,000,000 1.250.000 Rangers uses cost-to-cost to estimate the percentage complete on...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The proje...

    Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The project is to be completed by December 31, 2021, for a fixed price of $105 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Year Actual Cost Incurred each year Estimated to complete 2019 $ 20 million $ 80 million 2020 $ 45 million $ 25...

  • Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000....

    Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1.100.000 Estimated Cost to Complete $5,000,000 1,250,000 0 Rangers uses cost-to-cost to estimate the percentage complete on the contract. Provide the amount of gross profit recognized each year using two alternative revenue recognition methods. Year Completed Contract Method Percentage of Completion Method 2014...

  • 18.A construction company was hired on a construction project to build a building for $1,800,000. The...

    18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $450,000 $1,100,000 Estimated costs to complete 1,050,000 0 Billing during the year 400,000 1,400,000 Cash collections during the year 300,000 1,500,000 Assume that A recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT