A project is represented by the following diagram:
1. The expected duration of this project is:
A.12
B.17
C.20
D.36
E.77
2. The critical path for the network shown is:
A. a-c-g.
B. a-d-f-g.
C. a-d-h-i.
D. b-e-f-g.
E. b-e-h-i.
Calculating the time taken by following the each path, such as,
Path1= a-c-g = 4+3+6 = 13
Path2 = a-d-f-g = 4+5+ 2+6 = 17
Path 3= a-d-h-I = 4+5+1+3 = 13
Path 4= b-e-f-g = 5+7+2+6 = 20
Path 5= b-e-h-i =5+7 +1+3 = 16
Considering that the critical path is the longest sequence of activities in a project plan which must be completed on time for the project to complete on due date. Hence the expected duration of this project is 20 and the critical path for the network is “ b-e-f-g”.
Answer (1) C
Answer (2) D
A project is represented by the following diagram: 1. The expected duration of this project is:...
17-11) Use this network diagram for questions 11 through 17.
1. What is the expected duration of the project? (enter a whole
number)
2. What is the critical path for this project?
3. What is the early finish time for activity E?
4. What is the early start time for activity D?
5. What is the late finish time for activity C?
6. What is the late start time for activity B?
7. What is the slack time for activity...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
: A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...
Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points)
Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Develop a Network Diagram from the following chart (10 pts). You may either do your network diagram in WORD, DIA or another software program. You can also write out your diagram by hand (neatly please) and insert a picture of your drawing. Act. Dep. Dur. A 2 B 3 C 2 D A,B,C 12 E A,B,C 4 F E 2 G E 2 H F,G 3 I H,D 1 What is the Critical Path for this project? (eg. A ...
2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest completion time (LF) and slack for each of the following tasks (begin at time 0). Which tasks are on the critical path? Highlight the critical path on your network diagram [5] Activity Preceding Expected EF LF Slack Critical Event Duration Path? A 4 A 5 C A 6 A 7 E A, D 6 C, E 4 G D, E...
Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project?
The following information pertains to a project that is about to commence. Determine the duration of the Project, slacks, ES,EF,LS,LF & Critical path. Activity Precedes Estimated Duration (days) A B 15 B C, D 12 C E 6 D End 5 E End 3 F G, H 8 G I 8 H J 9 I End 7 J K 14 K End 6 ________________________________________