Question

A project is represented by the following diagram:

c, 3 C. a, 4 g. 6 d, 5 f 2 b. 5 i.3 h, 1

1. The expected duration of this project is:

A.12

B.17

C.20

D.36

E.77

2. The critical path for the network shown is:

A. a-c-g.

B. a-d-f-g.

C. a-d-h-i.

D. b-e-f-g.

E. b-e-h-i.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculating the time taken by following the each path, such as,

Path1= a-c-g = 4+3+6 = 13

Path2 = a-d-f-g = 4+5+ 2+6 = 17

Path 3= a-d-h-I = 4+5+1+3 = 13

Path 4= b-e-f-g = 5+7+2+6 = 20

Path 5= b-e-h-i =5+7 +1+3 = 16

Considering that the critical path is the longest sequence of activities in a project plan which must be completed on time for the project to complete on due date. Hence the expected duration of this project is 20 and the critical path for the network is “ b-e-f-g”.

Answer (1) C

Answer (2) D

Add a comment
Know the answer?
Add Answer to:
A project is represented by the following diagram: 1. The expected duration of this project is:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT