Question

Question 1: Create a project plan using Microsoft Office Project for the following project tasks. Project Name: Create a Webs

Q1, 2, and 3. Sorry for the trouble but if you could show how it should look like on microsoft project I would be thankful. Thank you for your help.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Project Scheduling or Plan created in MS Excel, Same way, it can be created in MS project software tool,

Project Name - Create a Website

Gantt Chart:

Here, Milestones are Zero duration activity, this milestone is significant activity, which talks about starting or ending of any project/ phase, Duration is in term of Day,

8 9 10 11 12 13 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 3132 33 34 35 36 37 33 39 40 414243 4 45 46 47 wies 13 Agree

2) Task relationships are shown according to the question requirement,

3) Critical Path for the above project - 1.1 - 1.2 - 1.3 - 2.2 - 2.3 - 3.1 -3.2, and Overall project duration is 48 Days, here 1 week = 7 Days considered,

Add a comment
Know the answer?
Add Answer to:
Q1, 2, and 3. Sorry for the trouble but if you could show how it should...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • 1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table...

    1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical Path (CP), the amount of slack and whether the task is a milestone. Task       Predecessors     Duration              CP (Yes/No)?        Slack (Amount)?   Milestone? PROJECT 2 A2 - 1    B2 A2    2 C2 A2 2 D2 B2, C2 3 E2 D2 2 F2 D2 3 G2 E2,F2 2 2. Draw a PERT (Network) chart for PROJECT 2. 3. Draw a...

  • About software project management Q2. Consider the following milestone table, what is the milestone trend chart...

    About software project management Q2. Consider the following milestone table, what is the milestone trend chart that the following project follows? Name and draw the milestone trend chart. Milestone Expected Delivery Actual delivery 1st month equirement Phase 2nd month 3rd month 4th month 5th month 6th month 7th month Installation/Training 8th montlh early 1 week time carly1 weck early 1 week early 2 weeks early 2 weeks early 2 weeks early 3 weeks Project Planning Analysis phase Design phase Coding...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • 2. Prepare a project schedule for Infotech software company. Assign the relevant resource Name and project...

    2. Prepare a project schedule for Infotech software company. Assign the relevant resource Name and project Starts Calculate the total duration of the project: InfoTech software development company to develop the software by the following task and subtask all the events are linear form. 5/7/2019 on 2. System Design 1.Software Requirement Specification Database Design (3 days) Detailed Design (2 days) Architectural Design (2 days) Requirement gathering (1 day) (3 days) (2 days) (2 days) Data collection Cost Analysis Risk Analysis...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a...

    Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...

  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • DSIM 350: Managing Product and Service Operations Final Exam - Total Points (100) Problem 2: Ch...

    DSIM 350: Managing Product and Service Operations Final Exam - Total Points (100) Problem 2: Ch 9 Project Management (50 Points) Following table gives the details about all tasks needed to be completed for a pro their respective predecessors and task times (weeks). ject along with 1. Activity Activity predecessor Time (Weeks) b, c 7 6 4 a. Draw the network diagram b. Calculate ES-EF-LF-LS times and determine the slack for each activity. Show all calculations on the diagram. Establish...

  • Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...

    Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT