Question
fill master production sechedule time phased record with lot size of 25 units. produce if inventory balance falls below 5
Fill Master Production Schedule time phased record with lot size of 25 units. Produce if inventory balance falls below 5 unit
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the updated master production schedule based on the details given.

Produce when inventory falls below 5 units

Available inventory (end) for current period = Available inventory (end) for previous period + MPS (if applicable) - Forecast

Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 10 10 15 15 15 15 15 15
Available inventory (End) 10 5 25+5-5=25 25-5=20 10 10+25-10=25 10 20 5 5+25-15=15 15+25-15=25 10
MPS 0 0 25 0 0 25 0 25 0 25 25 0
On hand inventory (Start) 15


Please give thumbs up/ likes if you find this answer helpful. Thank you!

Add a comment
Know the answer?
Add Answer to:
fill master production sechedule time phased record with lot size of 25 units. produce if inventory...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Management Instructions Beginning Inventory 68 Safety Stock 300 Lot Size 144 Master Production Schedule Period 1...

    Management Instructions Beginning Inventory 68 Safety Stock 300 Lot Size 144 Master Production Schedule Period 1 2 3 4 5 6 7 8 Demand 505 580 575 550 520 480 475 525 Customer Orders 710 660 570 330 100 515 80 40 Projected On-Hand Inventory (POHI) (at the end of the period) Master Production Schedule Available To Promise (1-period look ahead) Discrete Available To Promise (1-period look ahead) Cumulative

  • Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements...

    Recently, Phil Harris, the production control manager at Brunswick, read an article on time phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine...

  • i need help with 32-35 ASAP CONSIDER THE FOLLOWING PARTIALLY COMPLETED TIME-PHASED MASTER PRODUCTION SCHEDULE FOR...

    i need help with 32-35 ASAP CONSIDER THE FOLLOWING PARTIALLY COMPLETED TIME-PHASED MASTER PRODUCTION SCHEDULE FOR OUESTIONS 32-35 MPS QTY 20 On Hand 20 Lead Time 1 period 2 3 6 4 10 Forecast 10 10 10 10 10 10 Orders 12 5 9 5 Available 2 10 Available to Promise MPS 2 O (Received) 20 Ordered 32 The available value for week 1 should be 6 h 3 10 20 33 The available value for period 2 is 20...

  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and...

    Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and find out what is the available-to-promise. There are 20 units in beginning inventory and the lot size is 50. Answer in Excel and submit your answer in the drop box. Period 1 2 3 4 5 6 Forecast 20 22 23 20 25 20 Customers order (committed) 21 20 21 23 208 POH (Projected on hand) MPS (Master production schedule) ATP (Available-to-promise)

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products,...

    Question #3 Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Complete the following MPS time-phased record. Smell Fresh On Hand Week 1 2 3 4 5 6 7 8 Forecast 20 20 20 30 30 30 30 30 Orders 5 3 2 Projected available balance 20 50 30 10 30 50 20 40 10 Available to promise MPS 50 50 50 50 MPS Lot Size = 50 The following events...

  • Determine planned order releases for each part shown in the product structure tree. 180 units of...

    Determine planned order releases for each part shown in the product structure tree. 180 units of the finished product 565 are needed in week 6 (as shown in the master production schedule below). To figure out X43 material plan, look at planned order releases of both 565 and Y36. So, fill out X43 form after filling out 565 and Y36 plans. 565 X43 Y36(2) N78 J27(4) X43 Part Number On Hand Lot Size Lead Time 565 0 Lot-for-lot 1 week...

  • Analytics Exercise 9-1 Recently, Phil Harris, the production control manager at Brunswick, read a...

    Analytics Exercise 9-1 Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time phased requirements planning.      Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT