Frada, Co.Ltd. produces disinfectants by mixing 2 chemical solutions in a machine to become a disinfectant solution (solution 1 and solution 2). Solution 1 is the first process which is carried out at workstation A for 0.5 minutes per solution then continued at workstation B for 0.2 minutes per solution. Then together solution 1 is mixed with solution 2 at workstation C for 0.8 minutes per solution. Workstations B and C are processed at workstation D for mixing together where the process is 10 minutes per solution until it becomes a disinfectant solution for sale to customers.


a. Which workstations are the bottleneck? Explain with a picture of the workstation.
b. What is the resulting time (throughput time) of the entire work system above?
c. How much disinfectant solution can a company produce per hour?


1 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 8 more requests to produce the answer.

2 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Bottleneck Operations Management
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units.hr 1.8 units/hr Assembly a Sawing 0.8 units/hr Sanding Welding 5 units/hr Assembly 0.8 units/hr Driling 5 units.hr Assembly 0.8 units/hr a) Sanding is the bottleneck b) The bottleneck...

  • A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation...

    A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). Q 2.5 units/hr Sawing 2.1 units/he Sanding Assembly 0.8 unitsthe Welding 6 units.hr Assembly 0.8 units Drilling 5 unitshe Assembly 0.8 untui is the bottleneck 0.7 units/hr a) Drilling is the...

  • A diagram of a face-to-face service process is given below. There are four workstations (called "operations"),...

    A diagram of a face-to-face service process is given below. There are four workstations (called "operations"), each performing a different task with a single server at each. The expected demand is λ.-25 units per hour. Clerk B Clerk C Clek D w仍 OPI 40 cistomers bour bout 5. Determine the process times (in seconds per unit) for each of the activities. (2 pts) 6. Identify the bottleneck stage and determine the process capacity. (2 pts) 7. If the expected amount...

  • What is the process time of the system? b) What is the bottleneck time of this...

    What is the process time of the system? b) What is the bottleneck time of this work cell? c)What is the process cycle time? d) If the firm operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell? The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. o Capacity:...

  • John is installing a production line in the kitchen of his successful restaurant “Light of the...

    John is installing a production line in the kitchen of his successful restaurant “Light of the World” to make vanilla soufflé with caramel sauce. He figures his layout can be broken down into the following tasks: A. Egg separation – 8.5 min. B. Flour, milk, vanilla, egg yolk and sugar blend – 6.5 min. C. Fold egg whites into blend – 2.0 min. D. Bake – 8.9 min. E. Remove from oven, apply topping, garnish, stage, deliver – 8.0 min....

  • 8. A production line has three workstations. At station 1, there is one machine, which takes...

    8. A production line has three workstations. At station 1, there is one machine, which takes 2 minutes to process one unit. The unit then passes to station 2, which has two machines in parallel. The unit must be processed on just one of the machines at station 2, and each machine at station 2 takes 5 minutes to process one unit. The unit then passes to station 3, which has 6 machines in parallel. The unit must be processed...

  • 1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response...

    1. The bottleneck time of the system is - ??? minutes per unit ​(enter your response as a whole​ number). 2. Which Station (1, 2, or 3) is the bottle neck station? 3. The throughput time is - ?????? 4. If the firm operates 11 hours per? day, 5 days per? week, the weekly capacity of this work cell is?....... units? (enter your response as a whole? number). The three-station work cell illustrated in the figure below has a product...

  • A production line at V. J. Sugumaran's machine shop has three stations. The first station can...

    A production line at V. J. Sugumaran's machine shop has three stations. The first station can process a unit in 6 minutes. The second station has three identical machines, each of which can process a unit in 15 minutes (each unit only needs to be processed on one of the three machines). The third station can process a unit in 8 minutes ▼| is the bottleneck station, with a bottleneck time of] | minutes per unit (enteryourresponse as a whole...

  • NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has...

    NEED ANSWER D. The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 2 Station 3 5 min/unit 12 min/unit Station 1 Machine B 12 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3....

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT