Question

soon, hence you have to write your answer in the Texi-Field given below Actual Cost (AC). Planned Value (PV) and Eamed Value

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The formula for checking whether your project is ahead of the schedule or behind the schedule only comes from a easier earner value analysis

Schedule Variance = Earned Value – Planned Value

SV = EV – PV

From the above formula, we can conclude that:

  • You are ahead of schedule if the Schedule Variance is positive.
  • You are behind schedule if the Schedule Variance is negative.
  • You are on schedule if the Schedule Variance is zero.

Similarly for cost variance, we need the formula to calculate

Cost Variance = Earned Value – Actual Cost

CV = EV – AC

We can conclude the following from the above formula:

  • You are under budget if the Cost Variance is positive.
  • You are over budget if the Cost Variance is negative.
  • You are on the budget if the Cost Variance is zero.

We need to apply the above two formulas for each of the activity and comment

Add a comment
Know the answer?
Add Answer to:
soon, hence you have to write your answer in the Texi-Field given below Actual Cost (AC)....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • Given the project network and baseline information below, complete the form to develop a status r...

    Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 LEGEND ES | ID | EF SL LS DUR LF SL 8 D 12 0 8412 0 0 0 2 6 8 12 F15 0 12 315 0 0 0 7 E 10 2 93 12 2 4 5 9 Time Period Task LF DUR ES SL Budget (PV)...

  • Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important...

    Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below....

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • You have finished administering a food /drink questionnaire to ill and non-ill participants in a Minnesota...

    You have finished administering a food /drink questionnaire to ill and non-ill participants in a Minnesota summer picnic party. The ill individuals developed moderate to severe diarrhea 16 to 46 hours after the picnic. Six persons experienced vomiting. The following data were collected: ATE                                                    DID NOT EAT Number of people                               Number of people Food item                   Ill        Not ill      Total Ill        Not ill       Total Hot dogs                     40        30 70 10        20               30 Hamburgers                32        8         ...

  • Project: Managing a dinner party The case of Ahmad the liver maker Julia and John JJ...

    Project: Managing a dinner party The case of Ahmad the liver maker Julia and John JJ are going to give a dinner party on Friday evening at 07.00pm. Their two children, Jimmy and Jessy, are going to help them get ready. The JJs will all get home from work and school at 4.00pm. Julia and John have developed a project network to help them schedule their dinner preparations. Table below shows a list of the activities, the precedence relationships and...

  • Question 9 Below is the time phased baseline budget for a project and a table showing...

    Question 9 Below is the time phased baseline budget for a project and a table showing the progress as of End of Period 7. 2 Baseline PV Total Task Time Period PV 0 1 3 5 6 7 8 10 11 A 30 15 15 40 20 20 с 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 10 5 5 PV by...

  • This program is C++ You have just been offered your first big software contract. The scope...

    This program is C++ You have just been offered your first big software contract. The scope of work is to create a tool for grade school students to learn their times tables. In this program, you will create a 10 x 10 grid of times tables as a cheat sheet for the students to learn. This will display the values of the times tables all the way from 1x1 to 10x10. Make use of formatting tools like inserting tabs, setwidth(),...

  • Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...

    Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...

  • You have just finished administering a food/drink questionnaire to ill and non-ill participants in a Minnesota...

    You have just finished administering a food/drink questionnaire to ill and non-ill participants in a Minnesota summer picnic party. The ill individuals developed moderate to severe diarrhea 16 to 46 hours after the picnic. Six persons experienced vomiting. The following data were collected: ATE DID NOT EAT Number of people Number of people Food item Ill Not ill Total Ill Not ill Total Hot dogs 40 30 70 10 20 30 Hamburgers 32 8 40 20 40 60 Potato salad...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT