Question

The due date for a project is 20 weeks. If the expected activity times on a...

The due date for a project is 20 weeks. If the expected activity times on a noncritical

path is 19 weeks, what is the probability that this path will take more than 20 weeks? The variance of

the activities on this path is 4.16.

The probability is ......... percent. (Enter the closest whole number)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

z value (<=T) = (T - Expected time)/standard deviation

Expected time = 19

standard deviation = sqrt(Variance) = sqrt(4.16) = 2.04

z value (<=20) = (20-19)/2.04 = 0.49

Probability for completion in less than 20 weeks basis z value of 0.49 is 0.6880 or 68.80% (Using z table)

Probability that path will take more than 20 weeks is = 1 - 68.80% = 31.20% or 31%

Add a comment
Know the answer?
Add Answer to:
The due date for a project is 20 weeks. If the expected activity times on a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT